Description of the Korsnäs offshore wind farm project

The municipality of Korsnäs approved Metsähallitus’ planning initiative on the offshore wind farm in autumn 2020. The project site is located on a public water area managed by Metsähallitus, approximately 15 kilometres off the coast.

Wind turbines at sea

During the first phase of the project, 70 to 100 turbines with a nominal power of 12 to 20 megawatts would be built in the area. The Korsnäs project will thus become the first large-scale offshore wind farm in Finland after completed in the late 2020s.

The annual production of the offshore wind farm is estimated at about 5,000 GWh at this stage. For example, it would be enough to meet the electricity needs of 250,000 detached houses throughout the year, including electric heating. Finland’s first offshore wind farm in Tahkoluoto, Pori, produces about 155 GWh of electricity per year.

Project area was relocated due to natural values

The project site of 220 km2 is located on an area designated for wind power production in the Maritime Spatial Plan and an area reserved for wind power production in the regional land use plan for Ostrobothnia. The Maritime Spatial Plan is a strategic positioning document jointly formulated by key stakeholders in the marine area regarding the area’s sustainable use and the measures needed to maintain an adequate environmental status.

The location of the offshore wind farm was moved further south at the beginning of the project after the surveys. Project site is now located further away from the Kvarken World Heritage Site, nature reserves and from fish spawning grounds.

The final boundary of the area will be specified as planning progresses. It will be affected by considerations such as protected areas, the seabed, water depth and inclusive discussions with different stakeholders. Shipping routes in the area and the needs of the Finnish Defence Forces have also been taken into account in the location of the planning area.

Careful surveys of an area with ideal wind conditions

The wind conditions in the sea area off the Korsnäs shore are ideal. The average wind speed on the site may exceed 9 metres per second. The water depth and seabed geology are also well suited for wind power construction.

The sea. On the horizon wind farms.

The water depth at the project site is mainly 10 to 30 metres. The richest biodiversity of seabed organisms is found at depths of less than 10 metres. However, the benthic fauna in the area will be surveyed in detail as the project progresses.

Fishing and fish species have also been taken into account in the spatial planning of the project. Reefs and shallow areas important for fish reproduction are excluded from the project site. We have also examined the flyways of migratory birds and determined that the project site is far enough not to interfere with the flyways.

The wind farm site is located more than ten kilometres away from Kvarken Archipelago, the only natural heritage site in Finland on the UNESCO World Heritage List. Natura habitats are also located within sight of the project site. The impacts of the wind farm on these areas will be examined as part of the project’s permit process.

Three large ports in the neighbourhood

One of the preconditions for constructing an offshore wind farm is the availability of suitable ports. Three large ports can be found near the Korsnäs project site in Kaskinen, Kristiina and Vaasa. These ports are served by a railway, and we are currently analysing their operational and storage capacity.

To transmit electricity from the project site in Korsnäs to the mainland, submarine cables will be laid on the seabed. A power line built on the mainland will connect the offshore wind farm to the existing electricity grid.

Cargo ship in the port of Vaskiluoto

Discussions on the submarine cable

The company responsible for Finland’s electricity transmission network is Fingrid. We are currently negotiating with Fingrid on different options for connecting the wind farm to the main grid. These options will also be examined as part of the environmental impact assessment (EIA).

The conditions in Finnish sea areas are different from those in seas such as the North Sea as cold and ice require different technical solutions.

We believe that the development of offshore wind power will bring a new kind of know-how to Finland, and on the other hand create new opportunities for the development of existing core know-how.